Termination for Default (T4D)

Termination for default is the government's contractual remedy, under FAR Subpart 49.4 and the Default clause at 52.249-8, for a contractor's failure to deliver on time, make progress, or perform another contract provision. The contractor is paid nothing for undelivered work and owes the government's excess reprocurement costs.

The grounds are in FAR 49.402-1 and 52.249-8(a): late delivery, failure to make progress that endangers performance, and failure to perform any other provision. For the last two, the clause requires a written cure notice giving at least 10 days to fix the problem. Late delivery needs no cure notice, but 49.402-3 has the contracting officer send a show cause notice when practicable and copy either notice to the SBA area office when the contractor is small.

Under 49.402-2 the government owes nothing for undelivered work, can recover progress payments, can take title to completed supplies and manufacturing materials, and under 49.402-6 repurchases against the contractor's account and bills the difference. The decision is discretionary: 49.402-3(f) has the contracting officer weigh the excuse, the urgency of the need, and whether other sources exist.

The failure mode is the improper default. If the failure was excusable under 52.249-8(c), paragraph (g) converts the action to a termination for convenience and the government pays the settlement it meant to avoid. Under 42.1503(h) the notice, and any withdrawal or conversion, goes into FAPIIS within three calendar days, where the next source selection team will read it.

Regulatory Reference

FAR 49.402-1; FAR 49.402-2; FAR 49.402-3; FAR 49.402-4; FAR 49.402-6; FAR 49.402-8; FAR 49.607; FAR 52.249-8; FAR 42.1503(h)

RFO Status

The Part 49 model deviation carries the default framework over intact, with the 10-day cure notice, show cause notice, excess reprocurement cost recovery, and convenience conversion for excusable failures all retained; the proposed rule for Parts 3 and 49 (FAR Case 2026-007, published June 23, 2026) describes its subpart 49.4 edits as clarifying when a cure notice applies and when a show cause notice is practicable, and DoD adopted the model text through class deviation 2026-O0010 effective February 1, 2026.

Category

Processes & Methods

How AcqBot Helps

AcqBot drafts the cure notice and show cause notice from the FAR 49.607 formats with the contract's delivery dates and clause paragraphs filled in, checks that enough schedule remains for a 10-day cure before the contracting officer picks that route, builds the 49.402-3(f) factors into a decision memorandum, and tracks the three-day FAPIIS reporting deadline from the date the notice goes out.