Termination for Convenience (T4C)

Termination for convenience is the government's contractual right, exercised by written notice under a FAR Part 49 clause such as 52.249-2, to end all or part of a contract when that is in the government's interest. The contractor is paid for work done plus reasonable profit on it, never anticipatory profits.

The right lives in the termination clause, and FAR 49.101 limits its use to cases where termination is in the government's interest. Under FAR 52.249-2 the contracting officer issues a Notice of Termination; the contractor stops work as directed, terminates affected subcontracts, protects termination inventory, and submits a settlement proposal no later than one year from the effective date unless the contracting officer extends the period in writing.

Settlement is a negotiation, and FAR 49.201 says so: business judgment, not strict accounting, is the heart of it. The contractor recovers costs incurred on the terminated work and a reasonable profit on that work, but FAR 49.202 bars anticipatory profits and consequential damages, and FAR 49.203 applies a loss ratio when the contract would have lost money at completion. If nothing was incurred, the TCO executes a no-cost settlement.

Commercial contracts run on a different clause. FAR 12.403 excludes Part 49, and 52.212-4(l) pays a percentage of the contract price matching the work performed plus demonstrable termination charges, with no obligation to follow Part 31 cost principles. On the noncommercial side, the deadline is where contractors lose: miss the one-year window without a written extension and 52.249-2(j) takes the appeal right with it.

Regulatory Reference

FAR 49.101; FAR 49.201; FAR 49.202; FAR 49.203; FAR 49.206-1; FAR 52.249-2; FAR 12.403; FAR 52.212-4(l)

RFO Status

The Part 49 model deviation keeps the one-year settlement proposal window, but the proposed rule for Parts 3 and 49 (FAR Case 2026-007, published June 23, 2026) would cut it to 90 days, shorten inventory schedules to 60 days, and make settlement audits discretionary for the TCO; DoD adopted the model text through class deviation 2026-O0010 effective February 1, 2026.

Category

Processes & Methods

How AcqBot Helps

AcqBot drafts the Notice of Termination with the stop-work instructions the clause requires, tracks the settlement proposal and inventory schedule deadlines against the version of Part 49 the contract carries, and tests a proposed settlement against the FAR 49.201 through 49.203 principles before the TCO signs.