Small Business Subcontracting Plan
A small business subcontracting plan sets the subcontracting goals, administration, and reporting an other-than-small offeror must negotiate before award of a contract expected to exceed $900,000 ($2 million for construction), under FAR 19.702 and Section 8(d) of the Small Business Act.
When a contract with an other-than-small business is expected to exceed $900,000 ($2 million for construction of a public facility) and has subcontracting possibilities, the apparently successful offeror must submit a plan acceptable to the contracting officer before award (FAR 19.702). No plan means no award: the offeror is ineligible. Small businesses, personal services contracts, and work performed entirely outside the United States are exempt.
The plan sets separate goals for each small business category, expressed in dollars and as a percentage of planned subcontracting, names the program administrator, describes what will be subcontracted, and commits the prime to eSRS reporting under the clause at FAR 52.219-9. The thresholds date from the October 1, 2025 FAR inflation adjustment.
Goals are targets, but the effort behind them is enforceable. Failing to make a good faith effort to comply is a material breach under 15 U.S.C. 637(d)(9), and FAR 52.219-16 backs it with liquidated damages: written notice, then 15 working days to respond before damages are assessed.
Regulatory Reference
15 U.S.C. 637(d); FAR 19.702; FAR 19.704; FAR 52.219-9; FAR 52.219-16
RFO Status
The Part 19 model deviation eliminates subpart 19.7 and splits subcontracting plans between presolicitation section 19.109 and postaward section 19.302, with plan elements at 19.206-2 and the $900,000/$2 million thresholds carried over; GSA adopted the model text as class deviation RFO-2025-19 (issued September 26, 2025, effective November 3, 2025), DoD through class deviation 2026-O0037 (effective January 21, 2026), and Part 19 is not among the June 23, 2026 first-batch proposed rules. (verified September 17, 2026)
Category
Documents & Artifacts
How AcqBot Helps
AcqBot flags every acquisition crossing the $900,000 threshold during solicitation planning, builds the plan-review checklist from the 19.704 elements, and tracks eSRS reporting and goal attainment across option periods so a 52.219-16 breach determination rests on the record rather than on memory.
Related glossary entries
Justification & Approval (J&A)
A Justification & Approval (J&A) is the formal document required by FAR 6.303 to justify awarding a federal contract without full and open competition, citing one of seven statutory exceptions and approved at thresholds based on dollar value.
Performance Work Statement (PWS)
A Performance Work Statement (PWS) describes required outcomes and measurable performance standards for a services acquisition rather than prescribing how the work must be done, enabling contractors to propose their own methods under performance-based acquisition.
Statement of Work (SOW)
A Statement of Work (SOW) is the contract document that prescribes, in specific and directive terms, the tasks a contractor must perform, the deliverables due, and the schedule — placing responsibility for the approach on the government.
Statement of Objectives (SOO)
A Statement of Objectives (SOO) is a brief government document stating top-level acquisition objectives and desired outcomes, leaving offerors free to propose their own technical approach and performance work statement in response.