Stop-Work Order

A stop-work order is the contracting officer's written direction under FAR 52.242-15 halting all or part of contract work for up to 90 days while the government decides how to proceed. Before the period ends, the government must cancel the order or terminate the work it covers.

FAR 42.1303 makes stop-work orders available in negotiated fixed-price or cost-reimbursement supply, R&D, and service contracts when a work stoppage may be required (a program realignment, an engineering breakthrough) and, generally, only when work should pause pending a government decision and a supplemental agreement providing for the suspension is not feasible. The clause, 52.242-15, is prescribed at 42.1305(b), and the contracting officer should discuss the order with the contractor promptly after issuing it.

The clock is the discipline. An order can run 90 days plus any further period the parties agree to; within that window the contracting officer must cancel it or terminate the work it covers. If the order is canceled or expires, the contractor may seek an equitable adjustment in schedule, price, or both, asserted within 30 days after the stoppage ends — though the CO may act on a later claim if the facts justify it. Alternate I adapts the remedy for cost-reimbursement contracts, adjusting estimated cost, fee, and schedule.

Practitioners confuse the neighbors. Suspension of work (52.242-14) is the fixed-price construction and architect-engineer counterpart, and a post-award protest stoppage rides 52.233-3, Protest After Award, not this clause. Stopped work is not free either: the adjustment covers cost and time the stoppage added, and the records that prove it should start the day the order lands.

Regulatory Reference

FAR subpart 42.13; FAR 42.1303; FAR 42.1305(b); FAR 52.242-15

RFO Status

The Part 42 model deviation, adopted at GSA as class deviation RFO-2025-42 (issued September 30, 2025, effective November 3, 2025), compresses the part from 17 subparts to 13 and moves stop-work orders from subpart 42.13 to subpart 42.10 (Suspension of Work, Stop-Work Orders, and Government Delay of Work) without disturbing the 52.242-15 framework; Part 42 is not among the June 23, 2026 first-batch proposed rules. (verified September 16, 2026)

Category

Processes & Methods

How AcqBot Helps

AcqBot drafts the stop-work order with the scope and rationale 42.1303 expects, tracks the 90-day decision deadline and the contractor's 30-day assertion window, and keeps the cost documentation both sides will need if the pause turns into an equitable adjustment or a termination.