The Prompt Payment Act, 31 U.S.C. chapter 39, requires agencies to pay proper invoices by a due date, generally 30 days from receipt, and to pay interest automatically at the Treasury-published rate when they miss it. OMB implements it at 5 CFR Part 1315; FAR subpart 32.9 carries it into contracts.
Under FAR 52.232-25, the standard due date is the later of the 30th day after the designated billing office receives a proper invoice or the 30th day after acceptance, and acceptance is deemed to occur on the seventh day after delivery or performance unless the contract says otherwise. Construction progress payment requests are due in 14 days under FAR 32.904. Food moves faster: meat and fish within seven days of delivery, perishable produce and dairy within ten.
Miss the date and interest runs by itself. 31 U.S.C. 3902 sets the penalty at the rate the Treasury establishes and publishes in the Federal Register, accruing from the day after the due date until payment, owed without any request from the contractor. The clock also polices the government's paperwork: an agency has seven days to return an improper invoice with its defects identified, and days beyond that come off the payment period for the corrected one (5 CFR 1315.4).
The boundary practitioners miss is financing. The Act covers invoice payments, and contract financing payments sit outside it — a late progress payment under a financing clause accrues no Prompt Payment interest, while a final invoice for the same work does. Architect-engineer and construction contracts take their own clauses, 52.232-26 and 52.232-27.
Regulatory Reference
31 U.S.C. 3901-3907; 5 CFR Part 1315; FAR subpart 32.9; FAR 52.232-25
RFO Status
The Part 32 model deviation, adopted at GSA as class deviation RFO-2025-32 (issued October 7, 2025, effective November 3, 2025), retains subpart 32.9 and its prompt payment framework while revising other financing clauses; Part 32 is not among the June 23, 2026 first-batch proposed rules, and the statute and 5 CFR Part 1315 sit outside the FAR entirely. (verified September 15, 2026)
Category
Regulations & Policy
How AcqBot Helps
AcqBot dates each invoice from billing-office receipt, applies the correct due date — 30 days standard, 14 for construction progress requests, the accelerated food schedules — and computes the 31 U.S.C. 3902 interest exposure on anything trending late while there is still time to pay clean.
Related glossary entries
Class Deviation
A class deviation authorizes an agency to depart from specific FAR or supplement provisions for a category of contract actions rather than a single case — the mechanism agencies are using to implement the Revolutionary FAR Overhaul ahead of formal rulemaking.
Commercial Products and Services (FAR Part 12)
Commercial products and commercial services are items of a type sold, leased, licensed, or offered in the commercial marketplace, defined at FAR 2.101. FAR Part 12 implements the statutory preference for buying them whenever market research shows they can meet the agency's need.
Rule of Two
The rule of two directs a contracting officer to set aside an acquisition for small business when there is a reasonable expectation of receiving offers from at least two responsible small business concerns and making award at fair market prices, per FAR 19.502-2.
Controlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI) is information the government creates or possesses, or that an entity handles on its behalf, that a law, regulation, or governmentwide policy requires safeguarding or dissemination controls for — sensitive but not classified, governed by 32 CFR Part 2002.