Progress Payments

Progress payments are contract financing paid as work progresses on fixed-price contracts, computed under FAR subpart 32.5 as a percentage of incurred costs — customarily 80 percent, 85 percent for small businesses, and 90 percent for small businesses at DoD — and liquidated from later delivery payments.

The clause at FAR 52.232-16 pays a share of total incurred costs before anything ships: 80 percent customary, 85 percent for small businesses (FAR 32.501-1), and at DoD 90 percent for small businesses under DFARS 232.501-1. Customary financing takes a threshold — $3.5 million or more for other than small businesses, above the simplified acquisition threshold for small businesses (FAR 32.104(d)).

Delivery payments repay the government. FAR 32.503-8 sets the liquidation rate equal to the progress payment rate, and 32.503-9 lets the contracting officer lower it so a performing contractor keeps earned profit. Rates above customary are unusual progress payments, which 32.501-2 conditions on documented need and head-of-the-contracting-activity approval.

The rate is not an entitlement. Under 32.503-6 the contracting officer can reduce or suspend payments for delinquency in paying the costs of performance, excessive inventory, or a contract in a loss position, where the loss ratio shrinks the payable cost base — and on undefinitized contract actions the rate is capped at 80 percent by 10 U.S.C. 3804(b).

Regulatory Reference

FAR subpart 32.5; FAR 32.104(d); FAR 52.232-16; DFARS 232.501-1; 10 U.S.C. 3804(b)

RFO Status

The Part 32 model deviation (model text released September 30, 2025) simplifies the part and keeps progress payments based on costs, with 52.232-16 among the clauses updated; GSA adopted it as class deviation RFO-2025-32 (issued October 7, 2025, effective November 3, 2025) and DoD through class deviation 2026-O0022 (issued December 18, 2025, effective February 1, 2026), and Part 32 appears in neither the June 23, 2026 first-batch proposed rules nor the September 18, 2026 second batch. (verified September 18, 2026)

Category

Processes & Methods

How AcqBot Helps

AcqBot checks a candidate contract against the 32.104(d) financing gates, applies the correct customary rate for the contractor's size and agency, and builds the liquidation arithmetic — ordinary or alternate — into the payment schedule so the unliquidated balance stays visible through delivery.