Multiyear Contracting (MYP)

A multiyear contract buys more than one but not more than five program years of requirements under a single contract without annual options, per FAR subpart 17.1. Later years ride on annual funding; a negotiated cancellation ceiling caps the government's exposure if the money stops.

FAR 17.103 defines the type: one contract covering more than one but not more than five program years, with no option exercises between them (FAR subpart 17.1). Authority sits at 41 U.S.C. 3903 for civilian agencies and 10 U.S.C. 3501 for DoD. The government commits to the whole quantity at award and funds it one program year at a time.

When funding for a later year fails, the government cancels: a one-time act at the start of a program year that eliminates all remaining years, distinct from termination for convenience. The contractor recovers unamortized costs up to the cancellation ceiling set at award. DoD entry requires the findings at 10 U.S.C. 3501(a): savings or industrial base stability, a stable requirement, expected funding, stable design, realistic cost estimates. At or above $500 million, a DoD multiyear must also be specifically authorized by law in an act other than an appropriations act.

The recurring error is vocabulary. A contract with annual options is a multiple-year contract, not a multiyear one, and the difference is priced in: the firm commitment lets the contractor spread nonrecurring investment across every program year, with the cancellation ceiling standing behind the unrecovered balance.

Regulatory Reference

FAR subpart 17.1; 41 U.S.C. 3903; 10 U.S.C. 3501

RFO Status

The Part 17 model deviation keeps subpart 17.1 and restructures it: definitions move to 17.102 and policy to 17.103-1, which carries the 10 U.S.C. 3501 statutory tests including the $500 million certification. GSA adopted it as class deviation RFO-2025-17 (issued September 8, 2025, effective November 3, 2025) and DoD through class deviation 2026-O0027 (issued December 18, 2025); Part 17 is not among the June 23, 2026 first-batch proposed rules. (verified October 1, 2026)

Category

Contract Types & Vehicles

How AcqBot Helps

AcqBot builds the multiyear case file: it checks the requirement against the 10 U.S.C. 3501 findings, models cancellation ceilings by program year against the nonrecurring cost estimate, and drafts the determination and congressional notification package from the program's own numbers.