Liquidated Damages
Liquidated damages are preset amounts a contractor owes for late delivery or performance, used under FAR subpart 11.5 when timeliness matters, actual damage would be hard to prove, and the rate reasonably forecasts the Government's probable loss rather than punishing delay.
FAR 11.501 permits a liquidated damages clause only when two things are true: timely delivery or performance matters enough that the Government can expect to suffer damage from delinquency, and the extent of that damage would be difficult or impossible to estimate or prove. The rate must be a reasonable forecast of just compensation — maximums, capped periods, and graduated rates are allowed; punishment is not.
The clause and its rate go in the solicitation. For construction, FAR 11.502 builds the daily rate from estimated inspection costs plus other delay costs, such as renting substitute space. FAR 52.211-11 covers fixed-price supplies, services, and R&D, 52.211-12 construction; DFARS 211.503 makes 52.211-12 mandatory in DoD construction over $900,000 unless the contract is cost-plus-fixed-fee or the contractor cannot control the pace of the work.
Rates copied from a prior contract with no damage estimate behind them are the standing failure: an unsupported figure reads as punishment, which FAR 11.501 forbids. The contracting officer also owes mitigation — once default termination is in view, the regulation expects prompt action on performance or reprocurement.
Regulatory Reference
FAR 11.501; FAR 11.502; FAR 52.211-11; FAR 52.211-12; DFARS 211.503
RFO Status
The Part 11 model deviation (posted June 18, 2025; informal feedback closed August 4, 2025) retains liquidated damages coverage, renumbered from subpart 11.5 to 11.4; DoD adopted the rewrite through class deviation 2026-O0013 (effective February 1, 2026), covering DFARS 211. Part 11 appears in neither the first batch of proposed rules published June 23, 2026 (beginning at 91 FR 37550) nor the second batch published September 18, 2026 (beginning at 91 FR 59406), so published FAR subpart 11.5 and the 52.211-11 and 52.211-12 clauses remain the citations absent an agency deviation. (verified October 6, 2026)
Category
Regulations & Policy
How AcqBot Helps
AcqBot assembles the damage estimate FAR 11.502 expects behind the daily rate, writes the support into the contract file, and tracks accrual, excusable delay, and time extensions once delivery slips.
Related glossary entries
Class Deviation
A class deviation authorizes an agency to depart from specific FAR or supplement provisions for a category of contract actions rather than a single case — the mechanism agencies are using to implement the Revolutionary FAR Overhaul ahead of formal rulemaking.
Commercial Products and Services (FAR Part 12)
Commercial products and commercial services are items of a type sold, leased, licensed, or offered in the commercial marketplace, defined at FAR 2.101. FAR Part 12 implements the statutory preference for buying them whenever market research shows they can meet the agency's need.
Rule of Two
The rule of two directs a contracting officer to set aside an acquisition for small business when there is a reasonable expectation of receiving offers from at least two responsible small business concerns and making award at fair market prices, per FAR 19.502-2.
Controlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI) is information the government creates or possesses, or that an entity handles on its behalf, that a law, regulation, or governmentwide policy requires safeguarding or dissemination controls for — sensitive but not classified, governed by 32 CFR Part 2002.