Limitation of Cost / Limitation of Funds (LOC/LOF)
Limitation of Cost (FAR 52.232-20) and Limitation of Funds (FAR 52.232-22) cap the government's liability on cost-reimbursement contracts at the estimated cost or the funds allotted, and require written contractor notice as spending approaches the ceiling.
Which clause applies turns on funding: 52.232-20 goes in fully funded cost-reimbursement contracts and 52.232-22 in incrementally funded ones (FAR 32.706-2). Both run on the same trigger. When the contractor has reason to believe the costs it expects to incur in the next 60 days, added to all costs previously incurred, will exceed 75 percent of the estimated cost or of the amount allotted, it must notify the contracting officer in writing.
Under Limitation of Funds, the Schedule states the amount currently available for payment, and the government contemplates allotting more incrementally up to the full estimated cost. The contractor paces the work so that what the government has paid and owes approximates but does not exceed what has actually been allotted.
The ceiling is the point. The government is not obligated to reimburse costs above the estimated cost or the allotted total, and the contractor is not obligated to keep performing, until the contracting officer raises the figure in writing. A contractor that spends through the ceiling on the assumption that funds will follow has financed the overrun itself — notice buys a decision, not money.
Regulatory Reference
FAR 52.232-20; FAR 52.232-22; FAR 32.706-2
RFO Status
The Part 32 model deviation (posted September 30, 2025, with updated text October 9, 2025) keeps both clauses, listing 52.232-20 and 52.232-22 among those updated for clarity and cross-references; DoD adopted the deviated part through class deviation 2026-O0022 (issued December 18, 2025, effective February 1, 2026). Part 32 appears in neither the June 23, 2026 first-batch proposed rules nor the September 18, 2026 second batch. (verified October 2, 2026)
Category
Regulations & Policy
How AcqBot Helps
AcqBot tracks burn against the 75 percent threshold on every cost-type contract, drafts the 52.232-20 and 52.232-22 notices when the trigger approaches, and alerts the contracting officer and program office before an allotment runs dry mid-period of performance.
Related glossary entries
Class Deviation
A class deviation authorizes an agency to depart from specific FAR or supplement provisions for a category of contract actions rather than a single case — the mechanism agencies are using to implement the Revolutionary FAR Overhaul ahead of formal rulemaking.
Commercial Products and Services (FAR Part 12)
Commercial products and commercial services are items of a type sold, leased, licensed, or offered in the commercial marketplace, defined at FAR 2.101. FAR Part 12 implements the statutory preference for buying them whenever market research shows they can meet the agency's need.
Rule of Two
The rule of two directs a contracting officer to set aside an acquisition for small business when there is a reasonable expectation of receiving offers from at least two responsible small business concerns and making award at fair market prices, per FAR 19.502-2.
Controlled Unclassified Information (CUI)
Controlled Unclassified Information (CUI) is information the government creates or possesses, or that an entity handles on its behalf, that a law, regulation, or governmentwide policy requires safeguarding or dissemination controls for — sensitive but not classified, governed by 32 CFR Part 2002.