Letter Contract
A letter contract is a written preliminary contractual instrument under FAR 16.603 that authorizes a contractor to begin work immediately, before terms and price are settled. Definitization must follow within 180 days or completion of 40 percent of the work, whichever comes first.
The letter contract exists for the moment when work must start before a definitive contract can be negotiated: urgent repairs, a production line that cannot idle. Use requires a written determination by the head of the contracting activity, or a designee, that no other contract is suitable. Obligations are capped at the funds the contractor needs before definitization, and never more than 50 percent of the definitive contract's estimated cost without advance approval.
Each letter contract carries a negotiated definitization schedule under FAR 16.603-2: due dates for the proposal and certified cost or pricing data, a negotiation start date, and a target. Definitization must come within 180 days of award or before 40 percent of the work is done, whichever occurs first. Awards resting on price competition must include an overall price ceiling.
The bargaining problem is the familiar one: a contractor already performing has little reason to hurry toward price agreement. DoD runs its letter contracts as undefinitized contract actions under DFARS 217.74, with tighter obligation caps and a statutory definitization clock.
Regulatory Reference
FAR 16.603; FAR 16.603-2(c); FAR 16.603-3; DFARS 217.74
RFO Status
The Part 16 model deviation (posted September 30, 2025) retains letter contracts at 16.603-1 through 16.603-4 while adding section 16.104, the Executive Order 14402 justification regime for other-than-fixed-price awards. DoD adopted the rewrite through class deviation 2026-O0045 (issued February 20, 2026; Revision 1 effective March 16, 2026); Part 16 is not among the four first-batch proposed rules published June 23, 2026, so published FAR 16.603 remains the citation absent an agency deviation. (verified September 30, 2026)
Category
Contract Types & Vehicles
How AcqBot Helps
AcqBot drafts the no-other-contract-suitable determination, builds the definitization schedule into the contract file, and tracks each letter contract against the 180-day, 40 percent, and 50 percent liability triggers so definitization starts before the caps bind.
Related glossary entries
Other Transaction Authority (OTA)
Other Transaction Authority (OTA) lets certain agencies enter agreements for research, prototypes, and follow-on production that are not standard procurement contracts — largely exempt from the FAR — to attract nontraditional contractors and move faster than conventional acquisition allows.
Indefinite Delivery/Indefinite Quantity (IDIQ)
An Indefinite Delivery/Indefinite Quantity (IDIQ) contract buys an unspecified quantity of supplies or services, within stated minimum and maximum limits, over a fixed period. The government buys through task or delivery orders under FAR 16.504, with a preference for multiple awards.
Firm-Fixed-Price (FFP)
A firm-fixed-price (FFP) contract sets a price that is not subject to adjustment based on the contractor's cost experience in performance. FAR 16.202 places maximum cost risk on the contractor, who absorbs every overrun and keeps every underrun.
Cost-Plus-Fixed-Fee (CPFF)
A cost-plus-fixed-fee (CPFF) contract reimburses allowable costs and pays a fee negotiated and fixed at inception. The fee does not vary with actual cost, though it may adjust when the work changes. FAR 16.306 governs; statutory caps limit the fee.