Incremental funding obligates money to a contract in installments as funds become available rather than covering the full estimated cost at award; the Limitation of Funds clause at FAR 52.232-22 caps the government's liability at the amount allotted. FAR 32.703-1 governs.
FAR 32.703-1 recognizes two funding postures: fully funded, with funds obligated at award for the price or estimated cost and any fee, and incrementally funded, with funds covering only the amount allotted and its increment of fee. Incrementally funded cost-reimbursement contracts take the Limitation of Funds clause at FAR 52.232-22 in place of Limitation of Cost (32.706-2).
The clause runs on notice. The contractor must warn the contracting officer in writing when costs incurred plus those expected in the next 60 days will pass 75 percent of the total allotted, and 60 days before the funded period ends it states the additional funds needed to keep performing on time. Under 32.704, the contracting officer promptly answers whether more funds are coming.
The ceiling binds both sides. The government is not obligated to reimburse costs above the allotment, and the contractor is not obligated to keep performing past it; work beyond the allotment rides at the contractor's own expense. If funds are not allotted by the scheduled date, the contractor can require termination on written request.
Regulatory Reference
FAR 32.703-1; FAR 32.704; FAR 32.706-2; FAR 52.232-22
RFO Status
The Part 32 model deviation (posted September 30, 2025) carries contract funding forward at subpart 32.7, keeping incremental funding at 32.703-1 and limitation of cost or funds at 32.704; DoD adopted the deviated part through class deviation 2026-O0022 (issued December 18, 2025). Part 32 is not among the June 23, 2026 first-batch proposed rules, so published subpart 32.7 remains the baseline absent an agency deviation. (verified September 23, 2026)
Category
Processes & Methods
How AcqBot Helps
AcqBot tracks each allotment against incurred and projected cost, drafts the 75 percent and end-of-period notices the 52.232-22 clause requires with the dates the schedule sets, and warns the contracting officer when a 32.704 funding decision is due before the contractor's clock runs out.
Related glossary entries
Sources Sought Notice
A Sources Sought Notice is a pre-solicitation announcement, typically posted to SAM.gov, asking companies to identify their interest and capability to perform a prospective requirement — primarily used as market research to shape competition and set-aside decisions.
Request for Information (RFI)
A Request for Information (RFI) is a formal market research instrument used to gather industry input on capabilities, approaches, pricing structures, or draft requirements when the government is not yet ready to solicit — responses are voluntary and non-binding.
Lowest Price Technically Acceptable (LPTA)
Lowest Price Technically Acceptable (LPTA) is a source selection process that awards to the lowest-priced offeror whose proposal meets minimum acceptability standards — no credit is given for exceeding requirements, and tradeoffs between price and quality are not permitted.
Best-Value Tradeoff
The best-value tradeoff process permits award to other than the lowest-priced or highest-rated offeror when the source selection authority documents that the superior proposal's benefits are worth its price premium, or that a cheaper proposal's savings outweigh its weaknesses.