Excusable Delay

An excusable delay is a performance failure arising from causes beyond the contractor's control and without its fault or negligence — acts of God, government acts, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather — that shields the contractor from default.

The concept appears three ways. Cost-reimbursement, time-and-materials, and labor-hour contracts carry the standalone Excusable Delays clause, FAR 52.249-14, inserted per 49.505(b). Fixed-price contracts fold the same protection into the Default clause at 52.249-8(c). Commercial contracts state it at 52.212-4(f), which adds delays of common carriers to the familiar list and requires written notice as soon as reasonably possible after the delay begins.

Subcontractor failures get their own test. Under 52.249-8(d), a prime is not liable when the default originates with a subcontractor at any tier, the cause was beyond the control of both, and neither was at fault or negligent, unless the subcontracted supplies or services were obtainable from other sources in time to meet the schedule. The 52.249-14(b) version goes further: default attaches only if alternatives existed, the contracting officer ordered the contractor in writing to buy them, and the contractor failed to comply reasonably. On request, the contracting officer ascertains the facts and may revise the delivery schedule.

The standard has two prongs, and the second gets forgotten: the cause must be beyond the contractor's control and the contractor must be without fault or negligence in dealing with it. A listed cause proves nothing by itself — a strike the contractor could have mitigated, or weather no worse than the season usually brings, excuses nothing.

Regulatory Reference

FAR 52.249-14; FAR 49.505(b); FAR 52.249-8(c), (d); FAR 52.212-4(f)

RFO Status

The Part 49 model deviation (released August 21, 2025) left the termination clauses at 52.249-1 through 52.249-14 unchanged, and DoD adopted the model text through class deviation 2026-O0010 (issued December 18, 2025, effective February 1, 2026); Part 49 is in the June 23, 2026 first-batch proposed rules (FAR Case 2026-007, paired with Part 3; comments closed July 23, 2026), while the clause texts themselves sit in Part 52. (verified October 2, 2026)

Category

Regulations & Policy

How AcqBot Helps

AcqBot matches a reported delay against the excusable-cause tests in whichever clause the contract carries, drafts the contractor notice or the government response with the facts the record needs, and tracks whether the delivery schedule was revised so a later default action rests on a documented file.