Defense Priorities and Allocations System (DPAS)

The Defense Priorities and Allocations System (DPAS), at 15 CFR part 700, obligates suppliers to accept and fill rated orders for approved national defense programs ahead of other work. DX orders take preference over DO orders; both outrank unrated business.

The Commerce Department's Bureau of Industry and Security administers DPAS under Title I of the Defense Production Act (15 CFR part 700). Contracting officers place priority ratings on contracts under FAR subpart 11.6, and the rating then binds every supplier down the chain, whether or not they hold a government contract.

Acceptance is not optional. A supplier must accept a rated order it can fill and must answer in writing within ten working days for DX, fifteen for DO (15 CFR 700.13); rejection is allowed only on the grounds the rule lists, with reasons stated. Accepted orders get preferential scheduling under 700.14, including rearranging production already committed to unrated work, and 700.15 requires the recipient to place rated orders on its own suppliers for what it needs to perform.

The violations come from treating the rating as boilerplate. Letting the response clock run out in silence, serving a better commercial customer first, or dropping the rating from subcontract purchase orders each breaches the regulation itself, not merely the contract that carried it.

Regulatory Reference

Defense Production Act Title I, 50 U.S.C. 4501 et seq.; 15 CFR part 700; FAR subpart 11.6

RFO Status

The Part 11 model deviation strips Describing Agency Needs to its statutory core but keeps the priorities-and-allocations coverage. GSA adopted it as class deviation RFO-2025-11 (issued June 13, 2025, effective on issuance) and DoD through class deviation 2026-O0013 (issued December 18, 2025); Part 11 is not among the June 23, 2026 first-batch proposed rules. The system itself lives in 15 CFR part 700, outside the FAR's reach. (verified October 1, 2026)

Category

Regulations & Policy

How AcqBot Helps

AcqBot reads the priority rating on inbound contract actions, tracks the ten- and fifteen-working-day response deadlines, and checks that the rating flows onto every subcontract purchase order the requirement generates.