Cure Notice
A cure notice is the written notice FAR 49.402-3 requires before terminating a contract for default on any ground other than late delivery, specifying the failure and giving the contractor at least 10 days to cure it before termination may proceed.
Default grounds split in two. Failure to deliver on time needs no advance notice before termination. One that fails to make progress so as to endanger performance, or fails to perform another contract provision (such as not furnishing a required performance bond), must first receive a cure notice giving 10 days, or longer as necessary, to fix the failure (FAR 49.402-3).
FAR 49.607 supplies the formats and the timing rule: before the notice issues, at least the cure period must remain in the delivery schedule. With fewer than 10 days left the cure notice should not issue; the show cause notice takes its place, asking the contractor to explain within 10 days why the contract should not be terminated for default.
The trap is the clock. A cure notice granting 10 days when fewer remain in the schedule promises time the contract does not have, and a termination for failure to make progress with no cure notice behind it skips a step 49.402-3 makes mandatory.
Regulatory Reference
FAR 49.402-3; FAR 49.607
RFO Status
The Part 49 model deviation retains the cure notice framework at 49.402-3, with DoD adopting the model text through class deviation 2026-O0010 (issued December 18, 2025, effective February 1, 2026); the proposed rule for Parts 3 and 49 (FAR Case 2026-007, published June 23, 2026) refines subpart 49.4 to distinguish more clearly when a cure notice applies from when a show cause notice is practicable. (verified September 17, 2026)
Category
Documents & Artifacts
How AcqBot Helps
AcqBot drafts the cure notice from the 49.607 format, checks the remaining delivery schedule against the cure period before the notice goes out, and routes the show cause alternative when the clock is too short, with the file documentation to support whichever termination decision follows.
Related glossary entries
Justification & Approval (J&A)
A Justification & Approval (J&A) is the formal document required by FAR 6.303 to justify awarding a federal contract without full and open competition, citing one of seven statutory exceptions and approved at thresholds based on dollar value.
Performance Work Statement (PWS)
A Performance Work Statement (PWS) describes required outcomes and measurable performance standards for a services acquisition rather than prescribing how the work must be done, enabling contractors to propose their own methods under performance-based acquisition.
Statement of Work (SOW)
A Statement of Work (SOW) is the contract document that prescribes, in specific and directive terms, the tasks a contractor must perform, the deliverables due, and the schedule — placing responsibility for the approach on the government.
Statement of Objectives (SOO)
A Statement of Objectives (SOO) is a brief government document stating top-level acquisition objectives and desired outcomes, leaving offerors free to propose their own technical approach and performance work statement in response.