Cost-Plus-Incentive-Fee (CPIF)

A cost-plus-incentive-fee (CPIF) contract reimburses allowable costs and adjusts the initially negotiated fee by formula, comparing total allowable cost to target cost, within a negotiated minimum and maximum fee. FAR 16.405-1 governs.

The parties negotiate four numbers at the outset: target cost, target fee, and minimum and maximum fees, tied together by a fee adjustment formula (FAR 16.405-1). After performance the formula sets the fee: total allowable cost below target raises it, cost above target lowers it. Once cost passes either end of the formula's range, the contractor is paid allowable costs plus the minimum or the maximum fee.

The type fits services and development or test programs where a cost-reimbursement contract is necessary and the parties can negotiate a target cost and formula likely to motivate effective cost management. No CPIF contract may be awarded unless every limitation in FAR 16.301-3 is met, and performance incentives may be added where objectives can be measured.

The number that matters is where the share line hits the fee floor. Past that point the contract behaves as pure cost reimbursement, so a narrow band between minimum and maximum fee buys incentive paperwork without incentive effect.

Regulatory Reference

FAR 16.405-1; FAR 16.401; FAR 16.301-3

RFO Status

The Part 16 model deviation (posted September 30, 2025) consolidates CPIF coverage at section 16.405 within a restructured incentive subpart, and new section 16.104 (Executive Order 14402) pulls cost-reimbursement awards into the written-justification regime for other-than-fixed-price contracts; DoD conformed through class deviation 2026-O0045 (effective March 16, 2026). Part 16 is not among the June 23, 2026 first-batch proposed rules, so published 16.405-1 remains the baseline absent an agency deviation. (verified September 22, 2026)