Cost-Plus-Award-Fee (CPAF)
A cost-plus-award-fee (CPAF) contract reimburses allowable costs and pays a fee in two parts: a base amount fixed at inception, if any, and an award amount the contractor may earn in whole or in part through periodic government evaluations. FAR 16.405-2 governs.
CPAF fits work where predetermined objective incentive targets are neither feasible nor effective to devise (FAR 16.401(e)(1)). Using it takes a determination and findings signed by the head of the contracting activity, an award-fee plan approved by the fee-determining official, and an Award-Fee Board for each evaluation period (FAR 16.405-2; 16.401(d), (e)).
The fee rules have teeth. No award fee is earned for a period in which overall cost, schedule, and technical performance in the aggregate is below satisfactory, and rollover of unearned fee is prohibited (16.401(e)(2), (e)(4)). In DoD, base fee cannot exceed 3 percent of estimated cost exclusive of fee, at least 40 percent of the pool must remain available for the final evaluation unless the HCA approves less, and payments outside end-of-period evaluations are prohibited (DFARS 216.405-2).
The cost is administration. Each period needs a board, a rating, and a fee determination, and an office that cannot sustain that cadence has bought subjectivity without the machinery that makes it an incentive.
Regulatory Reference
FAR 16.405-2; FAR 16.401(d), (e); DFARS 216.405-2
RFO Status
The Part 16 model deviation (released September 30, 2025) consolidates award-fee arrangements at section 16.402, with cost-plus-award-fee at 16.402-4, and new section 16.104 (Executive Order 14402) requires written justification before other-than-fixed-price awards; DoD conformed DFARS 216 through class deviation 2026-O0045 (issued February 20, 2026; effective March 16, 2026). Part 16 is not among the June 23, 2026 first-batch proposed rules. (verified September 21, 2026)
Category
Contract Types & Vehicles
How AcqBot Helps
AcqBot drafts the 16.401(d) determination and findings and the award-fee plan skeleton, checks base fee and pool percentages against the DFARS 216.405-2 limits, and assembles the section 16.104 justification the Part 16 deviation now requires before a cost-reimbursement award.
Related glossary entries
Other Transaction Authority (OTA)
Other Transaction Authority (OTA) lets certain agencies enter agreements for research, prototypes, and follow-on production that are not standard procurement contracts — largely exempt from the FAR — to attract nontraditional contractors and move faster than conventional acquisition allows.
Indefinite Delivery/Indefinite Quantity (IDIQ)
An Indefinite Delivery/Indefinite Quantity (IDIQ) contract buys an unspecified quantity of supplies or services, within stated minimum and maximum limits, over a fixed period. The government buys through task or delivery orders under FAR 16.504, with a preference for multiple awards.
Firm-Fixed-Price (FFP)
A firm-fixed-price (FFP) contract sets a price that is not subject to adjustment based on the contractor's cost experience in performance. FAR 16.202 places maximum cost risk on the contractor, who absorbs every overrun and keeps every underrun.
Cost-Plus-Fixed-Fee (CPFF)
A cost-plus-fixed-fee (CPFF) contract reimburses allowable costs and pays a fee negotiated and fixed at inception. The fee does not vary with actual cost, though it may adjust when the work changes. FAR 16.306 governs; statutory caps limit the fee.