Contract Disputes Act (CDA)

The Contract Disputes Act, 41 U.S.C. 7101-7109, governs claims on federal contracts: a written demand to the contracting officer, certification above $100,000, a final decision on a statutory clock, then appeal to a board of contract appeals or the Court of Federal Claims.

The CDA channels every contract dispute through one gate: the contracting officer's final decision. A claim, defined in FAR 52.233-1 as a written demand seeking, as a matter of right, payment in a sum certain or other relief, must be submitted within six years of accrual. Above $100,000, the contractor certifies good faith, accurate and complete supporting data, an amount reflecting the government's liability, and the certifier's authority.

The clocks are statutory. A claim of $100,000 or less gets a decision within 60 days of a written request; a larger certified claim gets a decision within 60 days or a firm date for one. Interest runs from the day the contracting officer receives the claim (41 U.S.C. 7109). Appeal lies to the agency board within 90 days or the Court of Federal Claims within 12 months; performance continues in the meantime.

The trap is the line between an REA and a claim. A request priced as an opening position, or missing the sum certain, starts no clock and earns no interest — and the 90-day board deadline forgives nothing.

Regulatory Reference

41 U.S.C. 7101-7109; FAR subpart 33.2; FAR 52.233-1

RFO Status

The Part 33 model deviation, adopted at GSA as class deviation RFO-2025-33 (issued August 19, 2025, effective November 3, 2025), consolidates the claims procedures into a single Postaward section at 33.205 and rewrites the disputes clauses in plain language; Part 33 is in the June 23, 2026 first-batch proposed rules, which also revise 52.233-1. (verified September 14, 2026)

Category

Regulations & Policy

How AcqBot Helps

AcqBot tracks each claim from receipt — certification present where required, the 60-day decision clock, interest accruing under 41 U.S.C. 7109, the 90-day and 12-month appeal windows — and assembles the contracting officer's final decision from the contract record.