Contract Closeout
Contract closeout is the administrative wind-down of a physically complete federal contract: final payment, settlement of indirect cost rates where required, deobligation of excess funds, and closure of the file on the FAR 4.804-1 clocks — six months firm-fixed-price, 36 months where rates must settle.
Closeout begins when a contract is physically complete and ends when the file closes under FAR 4.804-1. The clocks run from evidence of physical completion: six months for firm-fixed-price contracts, 36 months for contracts requiring settlement of final indirect cost rates, and 20 months for everything else. Simplified acquisitions close on receipt of property and final payment. A file in litigation or under appeal stays open, as does a terminated contract with termination actions pending.
FAR 4.804-5 supplies the checklist: property clearance, final patent and royalty reports, releases executed, the final invoice paid, excess funds deobligated. On cost-reimbursement work the long pole is the 36-month clock, because final payment waits on settled final indirect rates. Quick closeout under FAR 42.708 shortcuts that wait when the unsettled direct and indirect costs on a contract or order do not exceed the lesser of $1 million or 10 percent of its amount.
The trade in quick closeout is finality. Rates negotiated that way are final for the contract they cover, no adjustment flows to other contracts for over- or under-recoveries, and the agreed rates set no precedent for later rate negotiations. For a contractor holding a healthy rate position that is the fastest route to the last dollar; for one expecting upward true-ups, it locks the loss in.
Regulatory Reference
FAR 4.804; FAR 4.804-1; FAR 4.804-5; FAR 42.708
RFO Status
The Part 4 model deviation, adopted at GSA as class deviation RFO-2025-04 (issued August 13, 2025, effective November 3, 2025), moves closeout from 4.804 and 4.805 to 4.308 and 4.309 in its postaward subpart; Part 4 is in the June 23, 2026 first-batch proposed rules, which relocate contract-file contents and internal procedures to the non-regulatory FAR Companion, and the companion Parts 3 and 49 proposed rule of the same date is aimed in part at accelerating closeout. (verified September 15, 2026)
Category
Processes & Methods
How AcqBot Helps
AcqBot builds the closeout queue from physical-completion evidence, runs the 4.804-5 checklist item by item on each contract, flags orders that fit the FAR 42.708 quick-closeout thresholds, and totals the funds waiting to be deobligated so the backlog is a number instead of a file room.
Related glossary entries
Sources Sought Notice
A Sources Sought Notice is a pre-solicitation announcement, typically posted to SAM.gov, asking companies to identify their interest and capability to perform a prospective requirement — primarily used as market research to shape competition and set-aside decisions.
Request for Information (RFI)
A Request for Information (RFI) is a formal market research instrument used to gather industry input on capabilities, approaches, pricing structures, or draft requirements when the government is not yet ready to solicit — responses are voluntary and non-binding.
Lowest Price Technically Acceptable (LPTA)
Lowest Price Technically Acceptable (LPTA) is a source selection process that awards to the lowest-priced offeror whose proposal meets minimum acceptability standards — no credit is given for exceeding requirements, and tradeoffs between price and quality are not permitted.
Best-Value Tradeoff
The best-value tradeoff process permits award to other than the lowest-priced or highest-rated offeror when the source selection authority documents that the superior proposal's benefits are worth its price premium, or that a cheaper proposal's savings outweigh its weaknesses.