Constructive Change

A constructive change is Government conduct — defective specifications, informal direction, acceleration after excusable delay, or a disputed contract interpretation — that requires work beyond the contract without a written change order, entitling the contractor to an equitable adjustment under the Changes clause.

The Changes clause lets the contracting officer order changes unilaterally, in writing, within the contract's general scope. The constructive change doctrine treats Government conduct with the same effect as if that order had issued: specifications that cannot be built as written, informal direction to perform the work differently, an acceleration demand after excusable delay, or a contract interpretation that proves wrong.

FAR 43.104 supplies the mechanics. A contractor that regards Government conduct as an unwritten change must notify the contracting officer in writing as soon as possible; the CO then confirms the change, countermands it, or responds that no change occurred. Confirmed changes are priced as equitable adjustments under the clause.

The recurring failure is authority. Under FAR 43.102(a), only contracting officers can execute modifications, and other Government personnel may not direct or encourage work that should be formalized. A contractor performing on a COR's say-so, without written notice, is financing the change itself — and the Government has a ratification problem.

Regulatory Reference

FAR 43.102(a); FAR 43.104; FAR 52.243-1

RFO Status

The Part 43 model deviation streamlines contract-modification coverage without substantive change to changes-clause mechanics; GSA adopted it through class deviation RFO-2025-43 (June 9, 2025) and DoD through class deviation 2026-O0034 (January 12, 2026), covering DFARS 243. Part 43 is not among the first-batch proposed rules published June 23, 2026 (beginning at 91 FR 37550), so published FAR 43.104 and the 52.243 clauses remain the citations absent an agency deviation. (verified October 5, 2026)

Category

Processes & Methods

How AcqBot Helps

AcqBot reads contractor change notifications against the contract file, drafts the confirm, countermand, or no-change response FAR 43.104 requires, and assembles the modification package when an equitable adjustment follows.