Consolidation and Bundling

Consolidation combines requirements previously bought under separate smaller contracts into one acquisition; bundling is consolidation that makes the result unsuitable for small business award. FAR 7.107 requires a written determination above $2 million for consolidation and measurably substantial benefits for bundling.

Bundling combines requirements previously performed under separate smaller contracts into a solicitation likely unsuitable for small business award because of the size, specialization, dollar value, or geographic spread of the work (15 U.S.C. 632(o)). Consolidation above $2 million takes a written determination by the senior procurement executive or chief acquisition officer that it is necessary and justified, backed by market research and less-consolidated alternatives (FAR 7.107; 15 U.S.C. 657q).

A bundle must also produce measurably substantial benefits: 10 percent of estimated value at $94 million or below, and 5 percent or $9.4 million, whichever is greater, above that (7.107-3(d)). Administrative savings alone do not qualify unless substantial relative to total cost. Substantial bundling ($8 million for DoD; $6 million for NASA, GSA, and Energy; $2.5 million elsewhere) adds strategy documentation on small business impediments and rejected alternatives.

The miss runs both directions: work never previously performed under separate smaller contracts cannot be bundled, and on a true bundle the benefit math gets skipped, the first place SBA procurement center representatives look.

Regulatory Reference

FAR 7.107; 15 U.S.C. 632(o); 15 U.S.C. 644(e); 15 U.S.C. 657q

RFO Status

The Part 7 model deviation (posted September 4, 2025) keeps 7.107 but collapses the separate consolidation, bundling, and substantial-bundling procedures into one standardized analysis, determination, and notification sequence, retaining the market-research predicate; GSA adopted it as class deviation RFO-2025-07 effective November 3, 2025, and DoD as class deviation 2026-O0020 (issued December 18, 2025). Part 7 is in the June 23, 2026 first-batch proposed rules (FAR case 2026-002, covering parts 6, 7, 10, 18, 26, 37, and 41), which carries the unified 7.107 forward; comments closed July 23, 2026. (verified September 25, 2026)

Category

Regulations & Policy

How AcqBot Helps

AcqBot flags a draft strategy that combines requirements small businesses previously performed, runs the 657q consolidation determination against its $2 million trigger, and computes whether projected savings clear the 10 or 5 percent benefit floors before the package reaches the senior procurement executive.