Changes Clause (FAR 52.243)

The Changes clause lets the contracting officer unilaterally order changes within the general scope of a contract — to drawings, specifications, method of shipment, or place of delivery — while obligating the contractor to keep performing. The contractor's remedy is an equitable adjustment under FAR 52.243-1 through 52.243-5.

Noncommercial FAR contracts carry a Changes clause matched to contract type: 52.243-1 for fixed-price, 52.243-2 for cost-reimbursement, 52.243-3 for time-and-materials and labor-hour, 52.243-4 for construction above the simplified acquisition threshold, and 52.243-5 below it (43.205). Commercial contracts work differently: under 52.212-4(c), changes to terms and conditions require written agreement of both parties. The contracting officer exercises the clause through a change order, a unilateral modification issued on Standard Form 30 under FAR subpart 43.2.

The bargain runs both ways. If the change drives cost or schedule up or down, the contracting officer makes an equitable adjustment to price, delivery, or both. The contractor must assert its right to an adjustment within 30 days of receiving the written order, and failure to agree on the adjustment is a dispute under the Disputes clause — never a license to stop. The clause says it plainly: nothing excuses the contractor from proceeding with the contract as changed.

Two doctrines do the real damage. A change outside the general scope, the cardinal change, exceeds the clause entirely: GAO and the Court of Federal Claims treat a modification materially different from the contract originally competed as a new procurement CICA requires the government to compete. And a contract can change without any SF 30. Government conduct the contractor considers a change (the constructive change) is what 52.243-7, Notification of Changes, exists to surface: prompt written notice to the ACO before the costs harden.

Regulatory Reference

FAR subpart 43.2; FAR 43.205; FAR 52.243-1 through 52.243-5; FAR 52.243-7; FAR 52.212-4(c)

RFO Status

The Part 43 model deviation, adopted at GSA as class deviation RFO-2025-43 (issued June 9, 2025, effective on issuance), trims about 300 words of non-statutory text while keeping the change-order framework intact; the Changes clauses themselves sit in Part 52, and Part 43 is not among the June 23, 2026 first-batch proposed rules. (verified September 16, 2026)

Category

Regulations & Policy

How AcqBot Helps

AcqBot drafts the change order and its SF 30, flags when a proposed change drifts outside the general scope before it becomes a cardinal-change problem, and tracks the 30-day assertion window and definitization status of every unpriced change order on the contract.