A bridge contract is a short-term, usually sole-source extension or stopgap award — generally to the incumbent — that keeps services running when the follow-on contract is not awarded before the current one ends. The FAR never defines the term; GAO and agency supplements do.

There is no FAR definition. GAO built one in GAO-16-15 (October 2015) after finding agencies had little insight into their own bridge use, and component supplements have followed — DISA's DARS 5817.000 defines a bridge as a short-term sole-source contract awarded generally to the incumbent to continue critical services when the follow-on could not be completed in time.

The first lever is the clause at 52.217-8, Option to Extend Services, which buys up to six months of continued performance at contract rates. Once that runs out, a bridge means a new sole-source action with a written justification, typically under FAR 6.302-1 (10 U.S.C. 3204(a)(1); 41 U.S.C. 3304(a)(1)) approved per FAR 6.303 and 6.304.

Bridges beget bridges. GAO found awards intended as stopgaps running past three years, and each successive bridge raises the cumulative value, the justification approval level, and the odds a competitor forces the issue — DISA requires every one to appear on its Bridge Report.

Regulatory Reference

FAR 52.217-8; FAR 6.302-1; FAR 6.303; GAO-16-15; DISA DARS 5817.000

RFO Status

The Overhaul supplies no bridge definition; the mechanics sit in Parts 6 and 17. The Part 6 model deviation and the June 23, 2026 first-batch proposed rule (91 FR 37636, comments closed July 23, 2026) restructure competition coverage without substantive policy change, and DoD adopted deviated Part 6 as class deviation 2026-O0017 (initially issued December 18, 2025). Part 17 is in the September 18, 2026 second-batch proposed rules (91 FR 59476, comments due October 19, 2026), which would rename 52.217-8 the Option to Extend, apply it beyond services, and let the parties toll the exercise window during a lapse in appropriations. (verified September 28, 2026)

Category

Contract Types & Vehicles

How AcqBot Helps

AcqBot watches the runway between a contract's end date and the follow-on's award milestones, flags when the 52.217-8 six-month extension will not cover the gap, and assembles the 6.302-1 justification with the acquisition-planning history the approval chain will ask about.